Sewerage
Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Pump Stations, STP and Sewer network work ongoing.

86% Completed

Water
Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Water & Sewerage
Ongoing

RO building internal piping work, RO plant installation, and PS EMD works. Both the outfall work (brine outfall and sea outfall) are in progress.

86% Completed

Ongoing

EMD works ongoing.

91% Completed

Completed [2023]

Water and Sewerage Networks are successfully completed.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Tank filling, PS finishing work ongoing.

91% Completed

Ongoing

Construction of STP (civil work), PS work ongoing (civil work), sewer network and house connection, and sea outfall work are in progress.

60% Completed

Ongoing

Electro mechanical design works and sea outfall works ongoing.

93% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Electro mechanical design works & Tank installation work ongoing.

98% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Construction of STP and PS work ongoing.

63% Completed

Ongoing

Construction of STP (civil work) and PS work ongoing(civil work) and Sea outfall work are in progress.

78% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2024]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Construction of RO building works are in progress.

60% Completed

Completed [2024]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

RO building internal piping work

89% Completed