Successfully completed the testing & commissioning.
100% Completed
Pump Stations, STP and Sewer network work ongoing.
86% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
RO building internal piping work, RO plant installation, and PS EMD works. Both the outfall work (brine outfall and sea outfall) are in progress.
86% Completed
EMD works ongoing.
91% Completed
Water and Sewerage Networks are successfully completed.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Tank filling, PS finishing work ongoing.
91% Completed
Construction of STP (civil work), PS work ongoing (civil work), sewer network and house connection, and sea outfall work are in progress.
60% Completed
Electro mechanical design works and sea outfall works ongoing.
93% Completed
Successfully completed the testing & commissioning.
100% Completed
Electro mechanical design works & Tank installation work ongoing.
98% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Construction of STP and PS work ongoing.
63% Completed
Construction of STP (civil work) and PS work ongoing(civil work) and Sea outfall work are in progress.
78% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Construction of RO building works are in progress.
60% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
Successfully completed the testing & commissioning.
100% Completed
RO building internal piping work
89% Completed